Construction group new xinzhuang town, minhang new town minhang new town, MHC10204 unit 19a-03a project image progress

2017-09-29 14:13:43

      Construction group xinzhuang town minhang new town minhang new town MHC10204 unit 19a-03a block project has completed the basement construction work and the roof waterproof layer.
The total PC external wall of the whole project is 2,327, and the prefabricated factory has produced 514 pieces, with a completion ratio of 22.1%. The total number of PC composite beams was 871, and 337 were produced. The PC composite board totalled 3,479 pieces and produced 542 pieces, which were completed by 15.6%. The PC air conditioning board totalled 1,613 pieces and produced 457 pieces, completing a total of 28.3%.
The 6th floor has completed a layer of casting work, installing a total of 34 PC external walls, 15 PCS stacked beams, 39 PC laminated plates, and 33 PC air conditioners.
The building of the fifth floor has been set up and the steel bar work is completed. Installed PC external wall 7 blocks.
A floor of the 4th floor has been built. The work of column, beam reinforcement and template has been completed. Installed PC external wall 56, PC composite beam 40.
One floor of the third floor has been set up, and the steel bar work has been completed.
The second floor of the second floor has been built and the steel bar work has been completed.
One floor of the first floor has been set up and the steel bar work has been completed. Installed PC external wall 32 blocks.
The total cost of the project is 319 million yuan, and the total value of the project is 110 million yuan, which is 34.5%. The installation of current water and PC enters the running water construction work. The staff of the resident project department will strictly control the safety and quality of the project to ensure the smooth completion of the project!

 